Wow...it's certainly been a busy few weeks for our data centre build. Over the past week we seem to have had 10+ contractors on site every day and it's all been GO, GO, GO!!!
The network cabling has been completed and the cooling guys are ahead of schedule on the installation of the pipework. The electrical contractors have completed…
Posted: October 12th, 2008 By: boost Read More →
Our data centre build is now well underway, with all building work now complete.
Currently we have a contractor installing 10Gb cabling under the floor to every single cabinet, as well as our environmental monitoring cabling. The environmental monitoring will keep track of each cabinet's temperature, humidity and power usages. In addition it will also monitor the performance…
Posted: September 11th, 2008 By: boost Read More →
We would like to announce that we have recently completed the purchase of a new property, which is to become our new data centre and operations site. The property will provide 12,000sq ft of floor space, dedicated to our data centre and operations teams.
[singlepic=3,300,150]
We are all very excited about the new facility, it will provide us with plenty of…
Posted: May 16th, 2008 By: boost Read More →